The papers for the next Morley Town Deal Board meeting have been published, so Iāve gone through them and pulled out the bits that are probably most relevant to residents.
The Town Deal is worth £24.3m, with projects covering the town centre, Town Hall, Skills Centre, parks, public realm and Morley Station.Ā
šļø Morley Town Hall
Work is continuing and the project is currently still reported asĀ within budget, although there are ongoing issues being worked through.
Scaffolding is now up around Alexandra Hall so the roof can be properly inspected. Most of the building issues have been identified and solutions are being developed. A new cafƩ floor has also been approved, while ventilation and fire-safety work is progressing.
The current target isĀ May 2027, although the milestone table identifies an estimatedĀ 11.5-week delay.Ā
š Morley Learning & Skills Centre
This is the biggest concern in the papers.
The project is currently ratedĀ RED. Work is continuing, but additional repairs are required to the plasterwork and roof timbers, with further structural issues found around the front of the building and roof supports.
The costs are still being assessed and there is a stated risk to the contingency budget. The anticipated completion date isĀ June 2027, with Luminate expected to fit out the building afterwards.Ā
š³ Parks and green spaces
There's quite a lot happening here:
- Scatcherd Park sunken garden works have started.
- Scatcherd Park playground works are next.
- Beryl Burton pocket park is going through the Traffic Regulation Order process, with work expected in early 2027.
- Tree planting in Drighlington is being explored.
- The Greenway is progressing, although one landowner issue remains.
The Greenway has agreements in principle with three landowners. One requires a Public Path Creation Order, with a "light touch" alternative being developed if agreement can't be reached.Ā
š¶ Queen Street / Commercial Street
A contractor has been appointed for theĀ Commercial Street and Queen Street pedestrian scheme, with works expected to start in October and last aroundĀ 16 weeks.
There are also three early schemes around Morley Station/Bilberry Bank due to start in October.Ā
šŖ Heritage shopfronts
The remaining Morley Bottoms/Queen Street shopfront works are expected to be completed byĀ October 2026.
The papers say the remaining programme budget will then be reallocated elsewhere within the wider Town Deal programme.Ā
š Morley Station
The Station Gateway programme remainsĀ green/amber, with enabling works around the station and Bilberry Bank starting in October.
The Station Road Traffic Regulation Order is expected to be completed in October, with wayfinding planned for early 2027.Ā
The overall picture
The programme is now well into construction, with the majority of projects progressing. The main areas to watch areĀ the Learning & Skills Centre and Town Hall, particularly the impact of building issues, contingency budgets and delays.
The papers say the overall programme is targeting completion of all projects byĀ June 2027, although the remaining public realm schemes are currently scheduled into summer/autumn 2027 and the Greenway is targeted for early 2027.Ā
One other interesting point:Ā the agenda includes a proposal relating toĀ Lewisham Community Centre, so that could be worth watching at the meeting too. The previous papers showed that a Community Asset Transfer proposal had been raised, with a business case required before it could be considered.Ā
The next Town Deal Board meeting isĀ 29 September at St Peter's Morley Community CentreĀ and the meetings are open to the public, with questions able to be submitted in advance.